The project incorporated a new central energy plant, including:
Hot water boilers
Three (3) new 250-ton roof-mounted air-cooled chillers
New heating hot water loop
Primary/Secondary chilled water loop – Incorporates variable speed drives on the primary and secondary pumps
Custom air handling units
Two emergency generators
Fire Suppression and Fire Alarm System
Complete coordination/installation drawings for the entire project produced, including Architectural, Structural, Civil, Mechanical, Electrical, Plumbing, and Fire Protection Engineering. Due to a strong focus on teamwork and communication, the project was completed on schedule and $600,000 under budget. The team considered the project to be a success, with all the project team members being recognized for their contribution at the grand opening ceremony.
Phasing was an integral part of the design. The existing facility remained in service throughout the construction phase.