Novant Health Charlotte Orthopedic Hospital

Hospital Renovation & Addition


Charlotte, NC

$67 Million construction value

89,500 square feet
  • Three-story replacement hospital, consisting of:
    • 7 operating rooms
    • 32 exam rooms
    • New sterile Processing and Distribution center
    • Physical therapy gymnasium
    • New Pre-Op/Post-Op
    • PACU area
  • The project incorporated a new central energy plant, including:
    • Hot water boilers
    • Three (3) new 250-ton roof-mounted air-cooled chillers
    • New heating hot water loop
    • Primary/Secondary chilled water loop – Incorporates variable speed drives on the primary and secondary pumps
    • Custom air handling units
    • Two emergency generators
    • Fire Suppression and Fire Alarm System
  • Complete coordination/installation drawings for the entire project produced, including Architectural, Structural, Civil, Mechanical, Electrical, Plumbing, and Fire Protection Engineering. Due to a strong focus on teamwork and communication, the project was completed on schedule and $600,000 under budget.  The team considered the project to be a success, with all the project team members being recognized for their contribution at the grand opening ceremony.
  • Phasing was an integral part of the design. The existing facility remained in service throughout the construction phase.